Questions & Answers for Request for Proposal DCS_LAN_RFP_24-25:
Q: I wanted to reach out and get clarification on a room at Selma Elementary. Thank you in advance for taking the time to look these over.
- In Selma Elementary – Classroom 3, there are five 5X data drops. How will those need to be terminated? Will there need to be multi-port wall plates, will each be terminated at a computer station?
A: Multi-port wall plates will be needed at the locations indicated on the map with multiple drops.
Q: Will there be any boring required at any of the schools?
A: Fortunately, the fiber that runs in between the MDF and IDF locations should not require any in-ground boring.
However, for detached buildings such as gyms, a conduit can be installed that is strapped to the awning over the walkway that connects the two buildings to facilitate the fiber connection.
received on 02.13.2024